PROJECT LOCATION
These curb ramp improvements are located at various locations identified as high priority for replacement throughout City Center.
PROJECT SCOPE
This project shall consist of: Removal of existing curb ramps, sidewalk, and traffic curb to be replaced with ADA compliant curb ramps in seven major locations in and around city center.
PROJECT SCHEDULE
Project opened bids on 7/31. Click here to view the bid results.
PROJECT FUNDING
This project is locally funded.
PROJECT UPDATE
10/2/25: Project started construction this week. We are targeting doing the ramp improvements on the west sides of the intersections first. Plans & contract docs can be found here.
PROJECT CONTACT
Charskie Kinloch, E.I.T.
Civil Engineer
(253) 835-2717
For additional details on this project or to find out more about other capital projects within Federal Way, click HERE to check out the City's interactive capital project map and dashboard.