PROJECT LOCATION

These curb ramp improvements are located at various locations identified as high priority for replacement throughout City Center.


PROJECT SCOPE

This project shall consist of: Removal of existing curb ramps, sidewalk, and traffic curb to be replaced with ADA compliant curb ramps in seven major locations in and around city center. 


PROJECT SCHEDULE

Project opened bids on 7/31. Click here to view the bid results.


PROJECT FUNDING

This project is locally funded.


PROJECT UPDATE

11/13/25: Construction is underway, plans & contract docs can be found here. Concrete pours for ADA Ramps at S 316th St & Pacific Highway South are happening this week. Single lane closures & two-way traffic maintained.


PROJECT CONTACT

Charskie Kinloch, E.I.T.

Civil Engineer

ckinloch@federalwaywa.gov

(253) 835-2717


For additional details on this project or to find out more about other capital projects within Federal Way, click HERE to check out the City's interactive capital project map and dashboard.