PROJECT LOCATION

Preservation of the pavement will take place on 21st Avenue SW between SW 320th Street & SW 339th Street.


PROJECT SCOPE

This project is a roadway pavement overlay. It includes ADA compliance upgrades to our curb ramps, asphalt planing and paving, pavement repairs, and channelization.  The project will improve driver safety; improve conditions for non-motorized users with ADA upgrades; and extend the life of the roadway surface.


PROJECT SCHEDULE

2025 - Design

2026 - Construction


PROJECT FUNDING

This project is federally funded through a WSDOT NHS Preservation Grant.


PROJECT UPDATE

Construction is underway for the 21st Ave SW Preservation Project.  This project includes:

  • Replacement of curb ramps and pedestrian push buttons to meet ADA standards
  • HMA pavement repair and overlay
  • Channelization and utility adjustments

 

TIMELINE:

Phase 1: Sidewalk and Curb Ramp Replacements

Daytime Work:  

June 22, 2026 to July 29, 2026

Monday - Friday between 6:30 A.M and 4:00 P.M.

Phase 2: Planing, Pavement Repair, Paving, and Channelization

Night Work: 

August 05, 2026 to September 29, 2026

Monday Night - Friday Morning between 8:00 P.M and 6:00 A.M.

*Timelines are estimates and may be adjusted due to weather.

 

WHAT TO EXPECT:

Approximately 30,000 cars travel on 21st Ave SW each day, so the City and contractors will do their best to minimize traffic impacts during this project. Expect increased travel times and plan ahead to avoid active construction.  In construction zones, remember:

  • Slow Down
  • Read Signs
  • Use alternate routes

Night work will occur for approximately one month.  During this time, nearby residences and businesses may be impacted by increased noise, vibrations, flashing lights, and lane closures.  Night work during this project is necessary to avoid severe daytime traffic disruptions and improve worker safety.


PROJECT CONTACT

Attiq Kazimi

Project Engineer

Attiq.Kazimi@federalwaywa.gov

253-835-2736


For additional details on this project or to find out more about other capital projects within Federal Way, click HERE to check out the City's interactive capital project map and dashboard.