PROJECT LOCATION

This project is located between S 317th St and S 272nd Street, primarily on Military Rd S and S 312th St.


PROJECT SCOPE

This project installs new conduit and fiber optic improvements to complete a fiber loop within the City's fiber network.  


PROJECT SCHEDULE

Construction is planned for 2024-2025.


PROJECT FUNDING

The funding for this project includes Sound Transit mitigation.


PROJECT UPDATE

6/25/25: Work on S 320th will begin later this month.  No traffic control should be needed.  This work will be to pull new fiber cable, and complete splicing connections.


PROJECT CONTACT

John Cole, E.I.T.

Civil Engineer

(253) 835-2718