PROJECT LOCATION
This project is located between S 317th St and S 272nd Street, primarily on Military Rd S and S 312th St.
PROJECT SCOPE
This project installs new conduit and fiber optic improvements to complete a fiber loop within the City's fiber network.
PROJECT SCHEDULE
Construction is planned for 2024-2025.
PROJECT FUNDING
The funding for this project includes Sound Transit mitigation.
PROJECT UPDATE
6/25/25: Work on S 320th will begin later this month. No traffic control should be needed. This work will be to pull new fiber cable, and complete splicing connections.
PROJECT CONTACT
John Cole, E.I.T.
Civil Engineer
(253) 835-2718
For additional details on this project or to find out more about other capital projects within Federal Way, click HERE to check out the City's interactive capital project map and dashboard.