PROJECT SCOPE

This project consists of: resurfacing the S 320th St from 1st Ave S to Pacific Hwy S; planing bituminous pavement; HMA repair; 2 1/2" thick HMA overlay; replacement of existing curb ramps and pedestrian push buttons to meet current ADA standards; removal and replacement of existing dual-faced sloped mountable curb; replacement of traffic signal detection loops; channelization and utility adjustments.

 

PROJECT SCHEDULE

Construction begins May 2026.

 

PROJECT FUNDING

The project is funded by PSRC and NHS Asset Management Program with a total amount of $3,000,000.

 

PROJECT MAP

S 320 St Vicinity Map

 

PROJECT CONTACT

Jeff Huynh

Civil Engineer